Anthony Licciardello | November 26, 2026
Scotch Plains
Union County · Development Update · November 2026 · Scotch Plains, NJ
The downtown plan did not move this month. The building that has to move first did. Scotch Plains has put a price of up to $49.5 million on a new Emergency Services Building on Plainfield Avenue, and the council takes it up on December 15.
In our guide to the Park Avenue rebuild we described a downtown being built in stages: two apartment buildings open, a supermarket under construction, and a nine-acre plan from Woodmont Properties still on paper. The news since then is about a different address. It is on Plainfield Avenue, away from the Village Green, and it is the piece that has to happen before the downtown plan can.
This update covers what the Township has announced since October, what it will cost, when the votes are, and what has not changed.
In a message dated November 6, Mayor Josh Losardo laid out the Township's plan for a new Emergency Services Building on Township-owned property on Plainfield Avenue. It would put the police, fire and EMS operations, the Office of Emergency Management, the Volunteer Rescue Squad and the municipal court under one roof.
The plan is smaller than the one residents saw before. The 2023 concept called for about 69,900 square feet at an estimated $67 million. The current plan is about 49,760 square feet, nearly 20,000 square feet smaller, with a projected cost of up to $49.5 million. That is a reduction of $17.5 million.
Approximate square footage as stated by the Township, November 2026.
Estimated and projected cost as stated by the Township, November 2026. The final cost will be set by competitive bidding.
The Township bought 2450 Plainfield Avenue in 2025, next to the original site. According to the mayor's message, that purchase let the building be placed farther from nearby homes, with landscaped buffers added.
The stated reasons for the move are practical. The existing emergency facilities are described as outdated and located in a flood hazard area, and the new site is on higher ground. The Township has been discussing a building on Plainfield Avenue since 2018. "A project of this importance deserves a transparent public discussion," the mayor wrote.
The Woodmont plan presented in May would replace the current library, town hall, fire department and the parking lots beside them with a town square, apartments and retail. Those buildings are in use. The fire department and the rescue squad cannot be moved out until there is somewhere for them to go.
That is the link between the two projects, and the Township has said so directly. Relocating emergency services, the mayor wrote, will allow the Township to redevelop the current municipal properties and create revenue where those tax-exempt sites generate none today. When the downtown plan was unveiled in May, local coverage reported that construction would begin with the public safety building, with a groundbreaking planned for 2027. In October the deputy mayor likewise wrote that construction on the Plainfield Avenue site is expected to start next year.
The financing runs the same way. The Township says it intends to pay for the building with proceeds from the sale and redevelopment of the current municipal properties, revenue from other redevelopment, available grants and remaining bond funds. A bond ordinance would authorize the financing. It would not require the full amount to be spent, and any construction contract would be awarded only after competitive bidding sets the final cost.
The mayor's message does not give the amount of the bond ordinance or an estimate of the effect on property tax bills. Those are the two numbers to listen for at the December 3 information session. The plan also depends on proceeds from downtown land that has not been sold and a downtown plan that does not yet have its state permit, so ask how the bonds are repaid if those proceeds arrive later than expected.
Near the building site, at 2435 Plainfield Avenue, is Memorial Field, a park of about 2.8 acres with a baseball field, a playground and a 9/11 memorial. In a message dated October 16, Deputy Mayor Matt Adams announced that the Township was awarded $2,000,000 from the Union County Improvement Authority's 2026 capital grant program to renovate it.
The estimated total cost of the project is $2,845,000, so the grant covers most of it, and the deputy mayor wrote that the program spares local taxpayers a matching-fund burden. Planned work includes a reconfigured ball field with a bullpen, batting cages, netting and a renovated backstop, covered dugouts, a renovated playground, stormwater upgrades and an enhanced 9/11 memorial. The Township expects the full project to take about 30 months, including roughly a year of construction.
The timing is tied to the building next door. The deputy mayor wrote that the park work gains economies of scale because the area can be built at one time, with the Emergency Services Building to be built starting next year.
Four items from our earlier coverage, and where each stands as of this writing.
Two new apartment buildings downtown, Scotch Plains Crossing and 18 FIFTEEN, have had their ribbon cuttings. We covered the first of them in our report on Scotch Plains Crossing.
The new downtown is real, and it is years from finished. We will show you what buyers are paying now for North Side homes near Park Avenue, and how to describe the redevelopment accurately when you sell.
The bond ordinance was scheduled for introduction at the council meeting of November 10. The hearing on December 15 is the public's chance to comment before a final vote. The revaluation runs on its own track, and we explain it in our guide to Scotch Plains property taxes and the 2027 revaluation.
If you are buying near Park Avenue because of the new downtown, read the sequence before you count on a date. The emergency building has to be financed, bid and built. Then the municipal sites have to be vacated and sold. The Woodmont plan still needs its state permit. Each step has its own vote or approval. Pay for the downtown that exists today, and treat the rest as upside.
“People ask me when the new downtown is coming, and the honest answer is that it starts on Plainfield Avenue. Until the police and fire departments have a new home, the land on Park Avenue cannot change. December 15 is the vote that tells you whether the first step is really under way.”
Buyers leaving New York for more space and a town center they can walk to are watching what Scotch Plains builds downtown. The Prodigy Team is licensed on both sides of the bridge, so we work with those buyers before they ever tour a New Jersey home. Our digital reach is built for that pipeline: a YouTube channel with more than 400,000 views over the past year, a relocation community of more than 26,500 members on Facebook, and more than 17 million impressions on Pinterest.
Our in-house aerial series, Above the Streets, shows a home in the context buyers care about: the lot, the block and the town around it.
Call 718-873-7345 or start with a home value review.
The Township projects a cost of up to $49.5 million for a building of about 49,760 square feet. The 2023 concept was about 69,900 square feet at an estimated $67 million. The final cost will be set by competitive bidding.
On Township-owned property on Plainfield Avenue. The Township bought 2450 Plainfield Avenue in 2025, next to the original site, which allowed the building to be placed farther from nearby homes.
A bond ordinance was scheduled for introduction on November 10, 2026. A public information session is set for December 3 at 7 p.m. at Town Hall, and the public hearing and possible final adoption are set for December 15.
The downtown plan would redevelop the current municipal properties, including the sites that now house emergency services. Those services have to move to Plainfield Avenue before that land can be redeveloped.
No. The plan was presented on May 18, 2026 and is still being refined. The Township lists the required NJDEP Individual Permit approvals as pending.
Sources and data notes. Emergency Services Building size, cost, funding and meeting dates: Township of Scotch Plains, Message from Mayor Josh Losardo, November 6, 2026; Patch, November 5, 2026; WMTR, November 10, 2026. Memorial Field grant: Township of Scotch Plains, Message from Deputy Mayor Matt Adams, October 16, 2026. Sequence of the downtown plan: Patch coverage of the May 18, 2026 public session. Woodmont plan and NJDEP permit status: Township of Scotch Plains Downtown Redevelopment page, as retrieved November 23, 2026. Master Plan and survey: Township of Scotch Plains, Message from Mayor Josh Losardo, October 9, 2026. Lidl deadline and revaluation dates: Township sources cited in our earlier Scotch Plains coverage. Information is deemed reliable but is not guaranteed and should be independently verified.